If Availability is 100%, Performance is 100%, and OEE is 90%, what is the Value Stream Quality percentage?

Get ready for the Lean Bronze Certification Exam. Study with flashcards and multiple choice questions, each question has hints and explanations. Boost your confidence and pass your exam!

Multiple Choice

If Availability is 100%, Performance is 100%, and OEE is 90%, what is the Value Stream Quality percentage?

Explanation:
OEE is made up of three factors that multiply together: Availability, Performance, and Quality. If Availability is 100% and Performance is 100%, their product is 1.0. With OEE at 90% (0.9), the remaining factor must be 0.9, which is the Quality portion. So the Value Stream Quality percentage is 90%. This means about 90% of produced items are good, while the remaining 10% are not acceptable, causing the OEE to be 0.9.

OEE is made up of three factors that multiply together: Availability, Performance, and Quality. If Availability is 100% and Performance is 100%, their product is 1.0. With OEE at 90% (0.9), the remaining factor must be 0.9, which is the Quality portion. So the Value Stream Quality percentage is 90%. This means about 90% of produced items are good, while the remaining 10% are not acceptable, causing the OEE to be 0.9.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy