If work-in-process is 10 pieces and cycle time is 2.5 days, what is the throughput rate?

Get ready for the Lean Bronze Certification Exam. Study with flashcards and multiple choice questions, each question has hints and explanations. Boost your confidence and pass your exam!

Multiple Choice

If work-in-process is 10 pieces and cycle time is 2.5 days, what is the throughput rate?

Explanation:
Throughput rate comes from the relation between work-in-process and cycle time: throughput = WIP / cycle time. With 10 pieces in process and a cycle time of 2.5 days per piece, you get 10 ÷ 2.5 = 4 pieces per day. So the throughput rate is 4 pieces per day. This assumes a steady state where the average WIP and cycle time are representative; the other options would misinterpret the relationship or assume different timing.

Throughput rate comes from the relation between work-in-process and cycle time: throughput = WIP / cycle time. With 10 pieces in process and a cycle time of 2.5 days per piece, you get 10 ÷ 2.5 = 4 pieces per day. So the throughput rate is 4 pieces per day. This assumes a steady state where the average WIP and cycle time are representative; the other options would misinterpret the relationship or assume different timing.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy