In a process with a takt time of 3 minutes and a pack-out quantity of 35 parts, the Pitch is

Get ready for the Lean Bronze Certification Exam. Study with flashcards and multiple choice questions, each question has hints and explanations. Boost your confidence and pass your exam!

Multiple Choice

In a process with a takt time of 3 minutes and a pack-out quantity of 35 parts, the Pitch is

Explanation:
Pitch is the interval between the starts of successive packs, tying the cadence to both takt time and batch size. With a takt time of 3 minutes per part and a pack-out of 35 parts, the time to complete one pack is 3 minutes × 35 parts = 105 minutes. So the pitch is 105 minutes, meaning a new pack would be started every 105 minutes to maintain the cadence with takt time.

Pitch is the interval between the starts of successive packs, tying the cadence to both takt time and batch size. With a takt time of 3 minutes per part and a pack-out of 35 parts, the time to complete one pack is 3 minutes × 35 parts = 105 minutes. So the pitch is 105 minutes, meaning a new pack would be started every 105 minutes to maintain the cadence with takt time.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy